review-honing-setupSupplied evidence required

Actual honing setup and stroke

Offline review with additional files and records

Scope and limits

Checks selected pre-hone bore, complete tooling/fixtures, nominal stock/contact and a qualified finite axial stroke.

This review is available through the separate offline tools. It does not run automatically when you upload a STEP file and requires the additional inputs described below.

Required inputs

Actual pre-hone CAD, mandrel/stones/support/shoes, fixtures, bore/relief selection, stroke and independently pinned process/allowance requirements.

Assessment limits

Complete through cylinder or supported enlarged blind relief only; fit does not predict removal, finish, cylindricity or honing success.